Cladding remediation works to an existing Holiday Inn Express to provide a successful EWS 1 B1 rating certification located on Cheriton High Street, Folkestone. The works comprise the design and construction of cladding remediation works, incorporating removal of existing cladding system; insertion of fire cavity barriers at designated areas; and reinstallation of existing cladding system, along with internal compartmentation remedial works. The hotel remained open to staff and guests during the works. TCC were responsible for managing the procurement of the initial reports and surveys to inform the works, procuring the Main Contractor, and administering the Building Contract during the completion of the works on site providing Project Management, Employer’s Agent, Quantity Surveying and Principal Designer services.